Riders showed up at the new Quarry Trailhead the morning of July 17 not entirely sure what they'd find. Blodgett Bike Hill had been promised, delayed, promised again, and delayed again since 2024, and the trailbuilders themselves had spent most of 2025 posting updates that amounted to "soon." By midday that Friday, the directional descents were rolling with tire traffic, the new bridges over the drainage cuts were holding, and the reroute around Fenceline was finally rideable start to finish. Two and a half years of on-again, off-again construction became, in the space of one afternoon, a trail system people could actually lap.
That kind of gap between what a project promises and when it lands is the whole story of Colorado Springs trails right now. Three different systems on three different sides of the city went through real change in 2026, on three unrelated timelines, and most people who hike or ride here are working off whichever fragment they happened to catch. Someone heard the bike trails finally opened. Someone else heard the canyon road was closed again and assumed it was the same multi-year bridge project from a few years back. Someone on the east side just watched a construction crew show up in August, months after everyone else's projects wrapped. None of those three things are the same story, and treating them as one is how people end up driving to a trailhead that's been open for two months, or avoiding one that reopened in July.
Blodgett Bike Hill is done. The rest of Blodgett isn't.
The trail system that opened July 17 covers only the southern portion of Blodgett Open Space, and it's worth being precise about what's actually rideable there. The city's release lists 2.5 miles of directional downhill bike-only trail on Blodgett Bike Hill, four miles of multi-use trail for hikers and mountain bikers, a half-mile regional connector, and a new 50-space trailhead at the Quarry lot, along with four new trail bridges and the closure of a long list of unauthorized social trails that had been eroding the hillside for years.
Colorado Springs Mountain Bike Association, the volunteer group that pushed for the bike-only descents in the first place, had been publicly tracking the slippage for a year: a target of late 2025 that quietly became mid-2026. The reroute of the old Fenceline trail was part of what took the extra time. The original alignment crossed onto Pike National Forest land the city doesn't manage, so the fix was to keep the upper section of Fenceline intact on Forest Service ground and build a new version, informally called Fenceline 2.0, entirely on city property, with multiple lines for different skill levels.
What's still ahead is the northern portion of the open space, where the city says roughly seven more miles of hiking-only and multi-use trail are planned by the end of 2026, closer to Blodgett Peak itself. As of late August, the region's overall trail status was listed as clear, but that status covers the section that's already built. If you're heading up expecting the full 384-acre network to be finished, you'll find the northern portion still in some stage of construction through the rest of the year.
The Cañon closure that confused everyone
If you heard North Cheyenne Cañon Road was closed sometime this summer and assumed it was the long-running bridge replacement project, you're thinking of a different closure. That project, three vehicular bridges rebuilt because they dated to the early 1900s, wrapped years ago. What closed the road this June was a storm.
In early June, heavy rain moved through the canyon and washed out an entire lane of North Cheyenne Canyon Road about a mile and a half up from the Starsmore Visitor and Nature Center. Gold Camp Road took damage too, with an unpaved section collapsing at the edge and debris covering several other stretches. Both roads closed to vehicles, though the park itself stayed open to hikers and bikers on the designated trails the entire time, which is why you may have seen people out there even while the roads were shut.
Crews spent weeks on the repair, and the city confirmed North Cheyenne Canyon Road reopened to vehicles the afternoon of July 18, with Gold Camp Road following close behind. A permanent guardrail installation was still pending when the road reopened, so intermittent lane closures were possible for a while after, but as of the most recent city updates, both roads are carrying normal traffic. Access to Helen Hunt Falls and the Powell lot for Seven Bridges Trail is back to standard as well. The park's history of construction closures makes it easy to assume any given closure is part of some ongoing multi-year project. This one wasn't. It was a single storm event, repaired on its own timeline, and already behind us.
Rock Island is just getting started
While the west side was finishing up, the east side was only beginning. City planning documents from earlier this year had penciled in a spring start for the next phase of Rock Island Trail, but ground didn't actually break until August 20, months behind that original target. It's a different kind of project than either of the others. The centerpiece is a 210-foot pedestrian bridge over Sand Creek, connecting the west and east sides of the trail, along with a pedestrian-activated flashing crossing at Peterson Road. The city's own estimate for this phase runs 10 to 12 months once work is underway, funded through a combination of the Pikes Peak Rural Transportation Authority, Colorado Department of Transportation grants, and the city's Trails, Open Space and Parks program.
That means anyone using Rock Island Trail through fall and into next year should expect an active work zone around the Sand Creek crossing, likely including detours or temporary trail closures near the bridge site as equipment moves through. It's the opposite situation from Blodgett and the Cañon: those two are now in their "recently reopened, come enjoy it" phase, while Rock Island is entering its "construction is the story for the next year" phase. If your regular loop touches Rock Island, this is the one to actually plan around this season.
Where that leaves a fall weekend
Put the three timelines side by side and the practical picture looks like this. Blodgett's southern section, including the bike-only descents and the Quarry Trailhead, has been open and rideable since mid-July, with more of the open space still under construction to the north through the rest of the year. North Cheyenne Cañon is fully reopened to vehicle traffic as of mid-July, following a storm closure that had nothing to do with the park's earlier bridge project, though drivers may still hit the occasional guardrail-related lane closure. Rock Island Trail, meanwhile, is heading into its most disrupted stretch yet, with construction around the Sand Creek bridge likely to run into next summer.
None of that is complicated once it's laid out, but almost nobody hears it laid out. What circulates instead is whichever single fact reached a given rider first, usually months out of date by the time it gets repeated. The trail system on the west side just had its biggest year of improvement in recent memory. The one on the east side is only now starting its own version of that same process. Fall in Colorado Springs is a genuinely good time to be back on Blodgett or through the Cañon. It's a good time to build in a detour around Rock Island.
Keeping track of what's actually happening on the ground, not just what got reported once and never updated, is the same instinct that goes into reading a neighborhood well before a client ever asks a question about it. If you're weighing a move near any of these trail systems, or just curious what a property's proximity to one of them is actually worth day to day, Lux Estates is glad to talk through it.